|
Power
The Government has,
since Independence, been giving priority to this sector.
As a result, the installed generation capacity has risen
from a mere 1,300 megawatt (MW) at the time of Independence
to more than 1,00,000 MW today. Along with the growth
in installed generation capacity, there has also been
a phenomenal increase in the transmission and distribution
(T&D) capacity. However, despite these achievements,
the power sector has not kept pace with the growth in
demand with the result that the country has always faced
energy crisis and peaking shortages.
The state electricity boards (SEBs), have,
in the past, played a significant role in the generation
and supply of power. But the present financial health
of the SEBs is not sound, to say the least. This is
mainly due to un-economic tariffs for agriculture, lower
slabs of domestic consumption and high T&D losses,
which often disguise large-scale theft, and low billing
and collection efficiency. This is the main roadblock
to attracting the much-needed private investment and,
in fact, has been one of the main reasons for the shortfall
in capacity addition from private sector projects. The
actual capacity addition during the Ninth Plan (1997-2002)
was 19,015 MW against a target of 40,245 MW. The other
major reasons for shortfall in the capacity addition
were delay in land acquisition and environmental clearances,
unresolved issues in fuel linkages, contractual problems,
resettlement and rehabilitation (R&R) problems and
law and order problems.
As far as the Tenth Plan 2002-2007 is
concerned, the Working Group Report on Power has envisaged
a capacity addition requirement of 46,939 MW during
the Plan period. However, keeping in view the status
of the ongoing, sanctioned and new projects in the pipeline,
the Planning Commission assessed that a capacity addition
target of the order of 41,110 MW (comprising 18,659
MW from on-going, 9,193 MW from projects cleared by
the Central Electricity Authority (CEA) and 13,258 MW
from new schemes) would be more realistic.
The Government proposes to enhance public
funding for the sector as well as encourage the public
sector undertakings (PSUs) to take up projects in joint
ventures with private investors and state governments.
As part of these efforts, the Accelerated Generation
and Supply Programme (AG&SP) is proposed to be extended
to provide funds to critical ongoing schemes at subsidised
interest rates. There is also a focus on initiating
suitable policy measures to accelerate the pace of hydro
power development as well as to make nuclear power generation
as competitive as power generation from other fuels.
The Government is making concerted efforts to channelise
adequate investment to ensure the completion of the
National Grid 2012. This would enhance the inter-regional
transfer of power and facilitate the optimum utilisation
of existing assets.
Power sector reforms were initiated in
1991 to encourage competition in each sub element of
the sector, namely, generation, transmission and distribution
under an independent and transparent regulatory regime.
With this objective in mind a Central Electricity Regulatory
Commission (CERC) has already been set up at the national
level and State Electricity Regulatory Commissions (SERCs)
set up in 19 states, 11 of which have issued tariff
orders. Private sector participation has also been set
in motion with the enactment of the Electricity Laws
(Amendment) Act in 1998. The draft Electricity Bill,
2001 has been introduced in Parliament which will replace
the existing three laws relating to electricity: the
Indian Electricity Act, 1910 as amended from time to
time; the Electricity (Supply) Act, 1948 as amended
from time to time; and the Electricity Regulatory Commission
Act, 1998.
The Electricity Bill recognises trading
of power as a distinct activity and permits SERCs to
allow open access in distribution of electricity in
phases that would ultimately encourage efficiency and
competition.
These reforms could be carried forward
aggressively to improve the financial health of the
SEBs. The issue of one-time settlement of dues payable
by SEBs to central power utilities (CPUs) has been addressed
by securitising the dues. It is likely to facilitate
further reforms in the sector. Reforms in the distribution
sector have been identified as the key area of reform.
The Accelerated Power Development Programme (APDP) was
initiated in 2000-01 in order to give a fillip to the
reform process in the power sector. One of the main
strategies identified in this regard is the development
of distribution plans/projects for all distribution
circles as centres of excellence that can be replicated
by the states in the later phase of distribution reforms.
Sixty-three such circles have been taken up initially
under APDP funding, which envisages metering of 11 KiloVolt
(KV) feeders, improvement/strengthening of sub-transmission
and distribution network, 100 per cent metering, establishment
of a management information system (MIS) to improve
billing, collection etc.
Power Sector Reforms
Apart from envisaging the setting up of
the CERC, the Common Minimum Plan formulated at the
Chief Minister's conference in December 1996 also accepted
the need for rationalisation of tariffs so that subsidised
sectors like agriculture would pay at least 50 per cent
of the average cost of supply within three years. The
establishment of SERCs had been envisaged by the State
Power Ministers' conference, also in December 1996.
Besides licensing and setting of performance
norms, the CERC was expected to set tariffs for all
generation and transmission utilities supplying power
across several states. The SERCs were expected to discharge
a similar function for state utilities. Most importantly,
the regulatory bodies were expected to encourage competition,
on a level playing field, in each sub sector, namely
generation, transmission, distribution and supply. Such
competition under an independent, adequate and transparent
regulatory regime was expected to yield the desired
efficiency gains. Accordingly, the Electricity Regulatory
Commissions Act, was passed in July 1998.
Nineteen states - Orissa, Haryana, Andhra
Pradesh, Uttar Pradesh, Karnataka, West Bengal, Tamil
Nadu, Punjab, Delhi, Gujarat, Madhya Pradesh, Arunachal
Pradesh, Maharashtra, Rajasthan, Himachal Pradesh, Assam,
Chhatisgarh, Kerala and Uttaranchal - have either constituted
or notified the constitution of SERCs. The SERCs of
Orissa, Andhra Pradesh, Uttar Pradesh, Maharashtra,
Gujarat, Karnataka, Rajasthan, Delhi, Madhya Pradesh,
Himachal Pradesh and West Bengal have issued tariff
orders.
The Electricity Laws (Amendment) Act was
passed in 1998 to enable private participation in the
power transmission sector. The Indian Electricity Grid
Code (IEGC) was established by the CERC in January 2000
to ensure grid discipline and set operation and governance
parameters for individual players in the T&D sector.
Trading of power has been recognised as a distinct activity
that would encourage efficiency and competition. The
Power Trading Corporation (PTC) was set up to facilitate
inter-state trading in power. The Availability Based
Tariff order notified by the CERC in January, 2000 is
a step towards encouraging greater reliability and efficiency
in generation.
Orissa, Haryana, Andhra Pradesh, Uttar
Pradesh, Karnataka, Rajasthan, Madhya Pradesh and Delhi
have enacted State Electricity Reforms Acts which provide
for unbundling/corporatisation of SEBs, setting up of
SERCs etc. The SEBs of Orissa, Haryana, Andhra Pradesh,
Karnataka, Uttar Pradesh, Delhi and Rajasthan have been
unbundled/corporatised.
Captive Power Generation
The industrial sector is the largest consumer
of electricity. Besides purchasing power from the utilities,
a number of industries, viz. aluminium, cement, fertiliser,
iron, steel, paper, sugar etc. have their own captive
power plants either to supplement the electricity supply
from the utilities or for generating electricity as
a by-product through co-generation. Captive power plants
are being set up by industries to meet their own power
requirements to enable them to tide over problems due
to power shortages and poor quality of supply. The Electricity
Bill, 2001 proposes to free captive generation and enable
captive generators to sell directly to other consumers
by wheeling power through the grid under an open access
regime. However, the Tenth Plan capacity addition has
been finalised based on the demand as per the Sixteenth
Electric Power Survey that excludes the demand met by
captive power plants.
In accordance with the guidelines issued
by the Ministry of Power, the following categories would
be eligible to install captive power plants:
- A consumer of electricity.
- A group comprising more than one consumer
as a joint venture.
- An actual user of power but not a consumer.
- A group of actual users of power, but
not consumers, as a joint venture.
- A group comprising both consumers and
actual users of power as a joint venture but excluding
`Generating Company' as defined under Section 2(4A)
of the Electricity (Supply) Act, 1948.
- If the captive plants falls under the
category of hydro or CO-generation plant, such plant
may be permitted, irrespective of its size and the
power supply position in the state.
- If the captive power plant is based
on coal or liquid fuel or gas and if the state is
deficit in power supply, the installation of the plant
could normally be allowed and the plant can be permitted
to have a capacity up to 200 per cent of the requirement
of the host industry.
- If the captive power plant is based
on coal, liquid fuel or gas and the state is surplus
in power, the installation of such captive plants
can still be considered in cases where the state/SEB
cannot guarantee uninterrupted supply or stipulated
quality of supply (within prescribed voltage and frequency
variations) required by the industry or a particular
process. Further, captive generation may also be permitted
if it is found, after a review of costs and tariffs,
to be more economical than grid supply.
- Banking facilities may also be provided
to the captive plants so that available capacities
are utilised to the extent possible and when required.
The rates for banking may be determined on mutually
agreed terms.
- Units in Special Economic Zones
(SEZ) and industrial estates may be allowed to set
up captive power plants liberally.
|